Skip to content

Weekly Update ~ 3.27.26

Asphalt paving to occur in four areas next week!

During the week of March 30, crews will be paving the following areas:

•  Maryland Pkwy, University Rd to Tropicana Ave (west half of the road)
•  Maryland Pkwy, Vegas Valley Dr to Desert Inn Rd (west half of the road)

There will be no change to existing traffic control, but watch for intermittent impacts to cross streets and driveways as equipment moves through the area. Following paving, traffic switches will occur in these areas.

Crews will also be placing the final layer of asphalt (called UTACS) in the following areas:

•  Bonneville Ave, MLK Blvd to 1st St
•  Carson Ave, Casino Center Blvd to 13th St

Please note: UTACS requires warmer temperatures, so the drop in temperatures next week may push this work to the following week.

Safe. Comfortable. Accessible Connections!

Welcome to the Maryland Parkway
Bus Rapid Transit (BRT) project.

Construction Progress

Construction Phasing

Work hours may be extended to maintain the project schedule. Watch for lane shifts as work progresses. Whenever possible, additional travel lanes will be provided. Business and residential access will be maintained. On-street parking will be impacted as work progresses.

cpm_map21
cpm_num1a
Maryland Pkwy, Russell to Tropicana

Work hours: 6am-4pm
One lane open in each direction
– Construction of sidewalk and install of streetlights, traffic switch between Reno and Tropicana followed by roadway removals on the east half

cpm_num2c
Maryland Pkwy, Tropicana to Flamingo

Work hours: 6am-4pm
One lane open southbound, two lanes open northbound
– Install of streetlights, construction of curb, gutter, and sidewalk, paving the west half (Tropicana Ave to University Rd) on March 30/31, followed by a traffic switch between Tropicana and Harmon

cpm_num3a
Maryland Pkwy, Flamingo to Desert Inn

Work Hours: 8pm-7am
Day: Two lanes open in each direction
Night: One lane open in each direction
– Install of waterline and conduit, traffic signals, miscellaneous concrete work

cpm_num4b
Maryland Pkwy, Desert Inn to Sahara

Work Hours: 8pm-7am
Day: Two lanes open in each direction
Night: One lane open in each direction
– Install of conduit, curb, and waterline, paving the west half (Vegas Valley Dr to Desert Inn Rd) on March 30/31, followed by a traffic switch

cpm_num5c
Maryland Pkwy, Sahara to Charleston

Work Hours: 5am-1pm
One lane open in each direction
San Pedro to Oakey: Final roadway striping and signage coming soon. Franklin to Charleston: Dry utilities, streetlights, preparing the inside lanes for paving in mid-April.

cpm_num6b
Maryland Pkwy/Rue 13, Bonneville to Carson

Work Hours: 5am-1pm
One lane open in each direction
– Traffic signals and coordination with NV Energy

cpm_num7b
Carson Ave, Casino Center Blvd to 13th St

Work Hours: 5am-1pm (Casino Center to 7th), 7am-3pm (7th to 13th)
One lane open in each direction
– Placing final layer of asphalt (weather dependent), traffic signals and coordination with NV Energy

cpm_num8a
Bonneville Ave, Casino Center Blvd to MLK Blvd

Work Hours: 5am-1pm
One lane open in each direction between I-15 and the railroad underpass
– Placing final layer of asphalt (weather dependent), median island install, sidewalk construction, placing concrete surfaces, and install of traffic signals

cpm_num9a
Alta Dr, MLK Blvd to Tonopah Dr

Work Hours: 5am-1pm
– Final clean-up work as needed

cpm_num10b
Tonopah Dr, Alta Dr to Wellness Way

Work Hours: 5am-1pm
– Final clean-up work as needed

cpm_num11a
Wellness Way, Tonopah Dr to Shadow Ln

Work Hours: 5am-1pm
– Final clean-up work as needed

Copyright ©2024 Regional Transportation Commission of Southern Nevada. All Rights Reserved.