Weekly Update ~ 3.27.26
Asphalt paving to occur in four areas next week!
During the week of March 30, crews will be paving the following areas:
• Maryland Pkwy, University Rd to Tropicana Ave (west half of the road)
• Maryland Pkwy, Vegas Valley Dr to Desert Inn Rd (west half of the road)
There will be no change to existing traffic control, but watch for intermittent impacts to cross streets and driveways as equipment moves through the area. Following paving, traffic switches will occur in these areas.
Crews will also be placing the final layer of asphalt (called UTACS) in the following areas:
• Bonneville Ave, MLK Blvd to 1st St
• Carson Ave, Casino Center Blvd to 13th St
Please note: UTACS requires warmer temperatures, so the drop in temperatures next week may push this work to the following week.
Safe. Comfortable. Accessible Connections!
Welcome to the Maryland Parkway
Bus Rapid Transit (BRT) project.
Construction Phasing
Work hours may be extended to maintain the project schedule. Watch for lane shifts as work progresses. Whenever possible, additional travel lanes will be provided. Business and residential access will be maintained. On-street parking will be impacted as work progresses.
Maryland Pkwy, Russell to Tropicana
Work hours: 6am-4pm
One lane open in each direction
– Construction of sidewalk and install of streetlights, traffic switch between Reno and Tropicana followed by roadway removals on the east half
Maryland Pkwy, Tropicana to Flamingo
Work hours: 6am-4pm
One lane open southbound, two lanes open northbound
– Install of streetlights, construction of curb, gutter, and sidewalk, paving the west half (Tropicana Ave to University Rd) on March 30/31, followed by a traffic switch between Tropicana and Harmon
Maryland Pkwy, Flamingo to Desert Inn
Work Hours: 8pm-7am
Day: Two lanes open in each direction
Night: One lane open in each direction
– Install of waterline and conduit, traffic signals, miscellaneous concrete work
Maryland Pkwy, Desert Inn to Sahara
Work Hours: 8pm-7am
Day: Two lanes open in each direction
Night: One lane open in each direction
– Install of conduit, curb, and waterline, paving the west half (Vegas Valley Dr to Desert Inn Rd) on March 30/31, followed by a traffic switch
Maryland Pkwy, Sahara to Charleston
Work Hours: 5am-1pm
One lane open in each direction
– San Pedro to Oakey: Final roadway striping and signage coming soon. Franklin to Charleston: Dry utilities, streetlights, preparing the inside lanes for paving in mid-April.
Maryland Pkwy/Rue 13, Bonneville to Carson
Work Hours: 5am-1pm
One lane open in each direction
– Traffic signals and coordination with NV Energy
Carson Ave, Casino Center Blvd to 13th St
Work Hours: 5am-1pm (Casino Center to 7th), 7am-3pm (7th to 13th)
One lane open in each direction
– Placing final layer of asphalt (weather dependent), traffic signals and coordination with NV Energy
Bonneville Ave, Casino Center Blvd to MLK Blvd
Work Hours: 5am-1pm
One lane open in each direction between I-15 and the railroad underpass
– Placing final layer of asphalt (weather dependent), median island install, sidewalk construction, placing concrete surfaces, and install of traffic signals
Alta Dr, MLK Blvd to Tonopah Dr
Work Hours: 5am-1pm
– Final clean-up work as needed
Tonopah Dr, Alta Dr to Wellness Way
Work Hours: 5am-1pm
– Final clean-up work as needed
Wellness Way, Tonopah Dr to Shadow Ln
Work Hours: 5am-1pm
– Final clean-up work as needed
(702) 676-1899
marylandparkway@rtcsnv.com
Copyright ©2024 Regional Transportation Commission of Southern Nevada. All Rights Reserved.
